Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to progress through
decision point 5 (Full Business Case with Finalised
Costs).
(i) In respect of the Wakefield South East Gateway (Kirkgate) the Investment Committee approved that:
(a) The Wakefield SE Gateway (Kirkgate) scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).
(b) Approval to the Combined Authority’s contribution of £1.6 million which will be funded through £1.6 million from the Local Growth Fund.
(c) The Combined Authority enters into a funding agreement with Wakefield Council for expenditure of up to £1.6 million from the Local Growth Fund.
(d) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report, which will be subject to the scheme remaining within the tolerances outlined in this report.
Report author: Polly Hutton
Publication date: 09/11/2020
Date of decision: 05/11/2020
Decided at meeting: 05/11/2020 - ARCHIVED - West Yorkshire and York Investment Committee
Effective from: 17/11/2020