Decision details

York Outer Ring Road - Phase 3 (Transport Scheme)

Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the York Outer Ring Road - Phase 3 scheme to proceed through Decision Point 3 (Outline Business Case) and work commence on Activity 5 (Full Business Case with Finalised Costs).

Decision:

 

That in respect of the York Outer Ring Road Phase 3 project the Investment Committee approved:

 

(a)        That the York Outer Ring Road Phase 3 project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).

 

(b)        That an indicative approval to phase 3 to the value of £2.174 million is given from the West Yorkshire plus Transport Fund towards a total scheme cost of £7.174 million with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)         That an indicative approval to the YORR programme to the value of £38.378 million, an increase from £38.276 million, is given from the West Yorkshire plus Transport Fund towards a total programme cost of £44.216 million, an increase from £38.926 million.

 

(d)        That future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

Report author: Andrew Norman

Publication date: 10/01/2020

Date of decision: 09/01/2020

Decided at meeting: 09/01/2020 - ARCHIVED - West Yorkshire and York Investment Committee

Effective from: 18/01/2020