Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the York Outer Ring Road - Phase
3 scheme to proceed through Decision Point 3 (Outline Business
Case) and work commence on Activity 5 (Full Business Case with
Finalised Costs).
That in respect of the York Outer Ring Road Phase 3 project the Investment Committee approved:
(a) That the York Outer Ring Road Phase 3 project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).
(b) That an indicative approval to phase 3 to the value of £2.174 million is given from the West Yorkshire plus Transport Fund towards a total scheme cost of £7.174 million with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(c) That an indicative approval to the YORR programme to the value of £38.378 million, an increase from £38.276 million, is given from the West Yorkshire plus Transport Fund towards a total programme cost of £44.216 million, an increase from £38.926 million.
(d) That future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.
Report author: Andrew Norman
Publication date: 10/01/2020
Date of decision: 09/01/2020
Decided at meeting: 09/01/2020 - ARCHIVED - West Yorkshire and York Investment Committee
Effective from: 18/01/2020