Decision details

A58 Beckett Street and York Street

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Description of the Key Decision to be taken Approval for the A58 Beckett Street and York Street scheme to proceed through Decision Point 3 (Outline Business Case) and work commence on Activity 4 (Full Business Case).

Decisions:

Resolved:  In respect of A58 Beckett Street & York Street -

That following a recommendation from the Investment Committee, the Combined Authority approves:

(a)      That the A58 Beckett Street and York Street proceeds through decision point 3 (Outline business case) and work commences on activity 4 (Full business case)

(b)       That an indicative approval to the total project value of £14.536 million is given from the Leeds Public Transport Investment Programme fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (FBC with finalised costs).

(c)        That future approvals are made in accordance with the assurance   pathway and approval route outlined in the submitted report including at decision points 4 and 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

Report author: Lisa Childs

Publication date: 13/01/2020

Date of decision: 09/01/2020

Decided at meeting: 09/01/2020 - West Yorkshire Combined Authority

Effective from: 21/01/2020