Decision details

White Rose Station

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the White Rose Station scheme to proceed through Decision Point 3 (Outline Business Case) and work commence on Activity 4 (Full Business Case).

Decisions:

Resolved:  In respect of White Rose Station -

That following a recommendation from the Investment Committee, the Combined Authority approves:

(a)      That the White Rose Station project proceeds through decision point (outline business case) and work commences on activity 4 (full business case). 

(b)       That indicative approval to the total project value of £5 million has been given from the LPTIP fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(c)        That development costs of £2.611 million are approved in order to progress the scheme to decision point 5 (full business case with finalised costs), taking the total project approval to £3.111 million.

(d)      That the Combined Authority enters into a Funding Agreement with the developer for expenditure of up to £1.9 million from the LPTIP Fund.

(e)      That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

Report author: Lisa Childs

Publication date: 13/01/2020

Date of decision: 09/01/2020

Decided at meeting: 09/01/2020 - West Yorkshire Combined Authority

Effective from: 21/01/2020