Bradford City Centre Heritage Properties - Conditioning House (Regeneration Scheme)

Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the Bradford City Centre Heritage Properties - Conditioning House scheme to proceed through Decision Point 3 (Outline Business Case) and work commence on Activity 5 (Full Business Case with Finalised Costs).

Decision:

(i)           That in respect of the Conditioning House scheme the Investment Committee approves:

a)        That the Conditioning House scheme proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs)

b)        That an indicative approval to the total project value of £1.5 million is given from the Local Growth Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total scheme cost is £13.847 million

c)         That future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

Report author: Polly Hutton

Publication date: 04/09/2019

Date of decision: 03/09/2019

Decided at meeting: 03/09/2019 - ARCHIVED - West Yorkshire and York Investment Committee

Effective from: 12/09/2019