Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
This scheme will create new or upgrade
existing facilities to improve the waiting environment and travel
information available.
PMO Reference: DFT-LPTIP-006E
Stage: 2 (Development)
Decision Point: 3 (Outline Business Case)
Resolved: That in respect of Transport Hubs and Connecting Communities following a recommendation from the Investment Committee, the Combined Authority approves:
(i) That the Transport Hubs Improvement and Public Transport Access scheme proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs).
(ii) That an indicative approval to the total project value of £8.905 million is given from the Leeds Public Transport InvestmentProgramme with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(iii) That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision points 4 and 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.
Publication date: 27/06/2019
Date of decision: 27/06/2019
Decided at meeting: 27/06/2019 - West Yorkshire Combined Authority
Effective from: 06/07/2019