Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the Wellington House
Accommodation scheme to proceed through Decision Point 4 (Full
Business Case) and work commence on Activity 5 (Full Business Case
with Finalised Costs).
The scheme reference code is WYCA-INT-001.
Resolved: That in respect of West Yorkshire Combined Authority Head Office Accommodation Project Investment Committee approves that:
(a) The West Yorkshire Combined Authority Head Office Accommodation
project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).
(b) An indicative approval to the total project cost of £6.847 million is given.
This will be funded entirely by the Combined Authority (from the approved
budget for Corporate Projects), with full approval to spend being granted
once the scheme has progressed through the assurance process to
decision point 5 (full business case with finalised costs).
(c) Future approvals are made in accordance with the assurance pathway
and approval route set out in the submitted report following a
recommendation by the Combined Authority’s Programme Appraisal
Team. This will be subject to the scheme remaining within the tolerances
outlined in the report.
Report author: Kate Thompson
Publication date: 12/06/2019
Date of decision: 11/06/2019
Decided at meeting: 11/06/2019 - ARCHIVED - West Yorkshire and York Investment Committee
Effective from: 20/06/2019