York Outer Ring Road (Phase 2)

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The scheme will deliver improvements to the roundabout at the junction of A1237, Monks Cross, and North Lane in York.
PMO Reference: WYTF-PA4-046
Stage: 2 (Development)
Decision Point: 4 (Full Business Case)

Decision:

Resolved:

In respect of York Outer Ring Road Phase 2 (Monks Cross) –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the York Outer Ring Road Phase 2 project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs)

(ii)        That an indicative approval to Phase 2 to the value of £3.585 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted  report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

Report author: Andrew Norman

Publication date: 14/12/2018

Date of decision: 13/12/2018

Decided at meeting: 13/12/2018 - West Yorkshire Combined Authority

Effective from: 22/12/2018