Decision details

A61S Bus Priority Corridor, Leeds

Decision Maker: West Yorkshire Combined Authority

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Scheme to progress through Decision Point 5 and work commence on Activity 6.

Decision:

Resolved:

 

In respect of A61S Bus Priority Corridor , Leeds –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

 

(i)         That the A61 South project proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs).

(ii)        That an indicative approval to the total project value of £14.15 million is given from the Leeds Public Transport Investment Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

Report author: Lisa Childs

Publication date: 14/12/2018

Date of decision: 13/12/2018

Decided at meeting: 13/12/2018 - West Yorkshire Combined Authority

Effective from: 22/12/2018