Glasshoughton Southern Link Road

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

PMO Reference: WYTF-PA4-035
Stage: 2 (Development)
Decision Point: 4 (Full Business Case)
This scheme is the provision of a 7.3 meter wide single carriageway road with footways and a segregated cycle route.

Decision:

Resolved:  In respect of Glasshoughton Southern Link Road –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)            That the Glasshoughton Southern Link Road project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).

(ii)          That an indicative approval to the total project value of £7.320 million is given from the West Yorkshire-plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)         That development costs of £245,000 are approved in order to progress the scheme to decision point 5 (full business case with finalised costs), taking the total project approval to £978,000.

(iv)         That the Combined Authority enters into an addendum to the existing funding agreement with Wakefield Council for additional expenditure of up to £245,000 from the West Yorkshire plus Transport Fund. This takes the total funding agreement amount to £978,000.

(v)          That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team.

Report author: Andrew Norman

Publication date: 12/10/2018

Date of decision: 11/10/2018

Decided at meeting: 11/10/2018 - West Yorkshire Combined Authority

Effective from: 20/10/2018