Decision Maker: West Yorkshire Combined Authority
Decision status: Information Only
Is Key decision?: Yes
Is subject to call in?: Yes
PMO Reference: BHY-WHF-002
Stage: 1 (Eligibility)
Decision Point: 2 (Case Paper)
This scheme is part of a wider programme to help households across
Leeds City Region lower their fuel bills and keep their homes
warm.
Resolved: In respect of the Warm Homes Fund round 2a -
That following a recommendation from the Investment Committee, the Combined Authority approves:
(i) That the Warm Homes Fund phase 2a proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs)
(ii) That an indicative approval is given to the total project value of £4.688 million and the Combined Authority funding contribution of £3.451 million with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).The remainder will be funded by local authority partners, social housing providers and match with private sector match funding on a case by case basis.
(iii) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.
Report author: James Brass
Publication date: 12/10/2018
Date of decision: 11/10/2018
Decided at meeting: 11/10/2018 - West Yorkshire Combined Authority
Effective from: 20/10/2018