Corridor Improvement Programme - A58 / A672

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

PMO Reference: WYTF-PA4-038A-7
Stage: 2 (Development)
Decision Point: 3 (Outline Business Case)

This scheme is a package of small scale transport interventions on the A58 / A672 corridor focused on highway improvements.

Decision:

In respect of the Corridor Improvement Programme - A58/A672 -

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)      That the Corridor Improvements Programme scheme - A58/A672 proceeds through decision point 3 and work commences on activity 4 (full business case)

(ii)    That an indicative approval to the total project value of £6.024 million is given to be funded from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)   That the development costs of £706,665 are approved in order to progress the scheme to decision point 4 (full business case), and that the Combined Authority issue an addendum to the existing Funding Agreement with Calderdale Council  for expenditure of up to £706,665 from the West Yorkshire plus Transport Fund taking the total approval to £941,665.

(iv)   That future approvals are made in accordance with the approval pathway and approval route set out in the submitted report, to include at decision points 4 and 5 through a delegation to the Combined Authority’s Managing Director. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.

Report author: Andrew Norman

Publication date: 06/08/2018

Date of decision: 02/08/2018

Decided at meeting: 02/08/2018 - West Yorkshire Combined Authority