Leeds City Centre Package (change request)

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

This is a transformational programme in Leeds City Centre to creating a world class gateway for the city. It will facilitate the expansion of the city centre, the regeneration of South Bank and supports Leeds in becoming High Speed 2 (HS2) and Northern Powerhouse Rail ready. The works required will involve closing City Square to general traffic, improvements to Armley Gyratory, highways reconfiguration on Leeds Southbank and junction works to the M621.

Decision:

Resolved:  In respect of the Leeds City Centre Package -

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the change request for Leeds City Centre Package (LCCP) to increase the funding contribution from the West Yorkshire plus Transport Fund from £36.5 million to £66.8 million is given indicative approval, that the LCCP package will now be delivered as four individual phases is approved and work continues on Activity 4 (full business case) for Phase 1 and on Activity 3 (outline business case) for Phases 2, 3 and 4.

(ii)        That the revised total package delivery cost of £149.8 million is noted of which indicative funding from the Combined Authority is £79.6 million. This will be funded from the West Yorkshire plus Transport Fund’s original allocation (£36.5 million), over-programming against the West Yorkshire plus Transport Fund’s requested as part of this report (£30.3 million) and Leeds Public Transport Investment programme (£12.8 million).

(iii)       That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report, including at decision point 5, which will be made through a delegation to Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This approval route will be subject to the scheme remaining within the tolerances outlined above.

Report author: Jacquie Boulton

Publication date: 28/06/2018

Date of decision: 28/06/2018

Decided at meeting: 28/06/2018 - West Yorkshire Combined Authority

Effective from: 06/07/2018