Decision details

A629 Halifax Road, phase 5

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

This project forms part of the overarching A629 Halifax to Huddersfield corridor improvement scheme that has been split into five separate phases. Phase 5 seeks to improve accessibility between Huddersfield and Halifax, and to the M62. It relates to the section of the A629 between the Ainley Top roundabout and Huddersfield. The scheme includes capacity improvements from the Cavalry Arms junction to Ainley Top, with improvements at the Blacker Road junction.

Decision:

Resolved:  In respect of A629 Halifax Road improvement, phase 5 –

 

That following a recommendation from the Investment Committee the Combined Authority approves:

 

(a)      That the WYTF (Transport Fund) A629 Halifax Road Phase 5 project  proceeds through decision point 3 and work commences on activity 4 (full business case).

 

(b)      That an indicative approval to the total project value of £12.09 million is given from the Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)      That development costs of £4.113 million are approved in order to progress the scheme to decision point 4 (full business case), taking the total project approval to £4.418 million and that an addendum to the funding agreement with Kirklees Council for the additional £4.113 million is entered into.

 

(d)      That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision point 4 (full business case) through Investment Committee and Combined Authority and at decision point 5 (full business case with finalised costs) through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team.  This will be subject to the scheme remaining within the tolerances outlined in the submitted report.

Publication date: 11/05/2018

Date of decision: 10/05/2018

Decided at meeting: 10/05/2018 - West Yorkshire Combined Authority

Effective from: 19/05/2018