The approved extension to the loan repayment
date for this scheme, which involves the remediation of a former
chemical works to unlock the delivery of a low carbon power
station, and wider commercial and residential development to the
east of Knottingley, Wakefield, will allow time for further
geotechnical testing to be carried out on the site once ground
conditions allow, thus enabling the signing off of the end of works
Validation Report which in turn would allow for completion of sale
of the site under the terms of the sale agreement, and for
Wakefield Council to discharge planning conditions.
Decision Maker: Chief Executive
Decision published: 16/02/2018
Effective from: 09/02/2018
Decision:
To approve the Change Request for the
Knottingley East scheme to: extend the Growing Places Fund (GPF)
loan repayment date for from 15th February 2018 to 30th September
2018 or within 30 days of the sale of the land, whichever is
sooner, at an interest rate on the entire capital sum for the
period of the loan repayment of 4.54%.
To approve that WYCA instructs Leeds City Council to enter into an
addendum to the existing funding agreement with St Pauls
Developments Ltd to move the loan repayment deadline from 15th
February 2018 to 30th September 2018 or within 30 days of the sale
of the land, whichever is sooner.
Lead officer: Chris Brunold
To allow Network Rail to complete pre-nesting
works by 1st March 2018 to ensure the main contract to deliver 203
new car parking spaces at Mytholmroyd station, as part of the WY+TF
Rail Park & Ride Phase 1 Programme, can be delivered without
further slippage.
Decision Maker: Director, Finance & Commercial Services
Decision published: 16/02/2018
Effective from: 02/02/2018
Decision:
To approve the Change Request for the Rail
Park & Ride Programme - Mytholmroyd pre-nesting works to allow
for de-vegetation works to be carried out in advance of the 2018
nesting season and to approve advanced spend of up to £30,000
from the original total scheme funding allocation of £3.64m
to progress this work.
To approve WYCA entering into an Implementation Agreement with
Network Rail for the value of up to £30.000.00 for the works
to be undertaken.
Lead officer: Sara Brook
Leeds District Heat Network –
Infrastructure funding.
Decision Maker: Chief Executive
Decision published: 15/02/2018
Effective from: 19/01/2018
Decision:
Approval for WYCA to enter into the Funding Agreement with Leeds City Council for the Leeds District Heat Network for expenditure of up to £4m towards the total project costs for the Leeds District Heat Network of £21.276m.
Lead officer: Polly Hutton