Wyke Beck Valley Flood Alleviation

01/02/2018 - Wyke Beck Valley Flood Alleviation (Decision Point 4 Full Business Case)

Resolved: In respect of Wyke Beck Valley Flood Alleviation (Decision Point 4 Full Business Case)

 

That following a recommendation from the Investment Committee, WYCA approves:

 

(a)       That the Wyke Beck Valley Flood Alleviation Project proceeds through Decision Point 4 and work commences on Activity 5 (Full Business Case with Finalised Costs).

 

(b)       That an indicative approval to WYCA’s contribution of £2.600m (which will be funded through from the Local Growth Deal 3 fund) is given with Full Approval to spend being granted once the scheme has progressed through the Assurance Process to Decision Point 5 (FBC with Finalised Costs).

 

(c)        That future approvals are made in accordance with the Approval Pathway and Approval Route set out in this report, including at Decision Point 5 through a delegation to WYCA’s Managing Director following a recommendation by WYCA’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.