Issue - decisions

Energy Accelerator - FBC Appraisal Report

06/10/2017 - Energy Accelerator - FBC Appraisal Report

(vi)       In respect of the Energy Accelerator Programme –

 

That following a recommendation from the Investment Committee, WYCA approves:

 

(a)        That the Energy Accelerator Programme proceeds through Decision Point 4 and work commences on Activity 5 (Full Business Case with Finalised Costs).

 

(b)        That approval to spend the £0.640m Local Growth Fund allocation as match to support the development of the Accelerator be confirmed.

 

(c)        That an indicative approval to the to the £2.997m ELENA funding (exact amount dependent on Euro exchange rate at the date of approval – application pending) is given with Full Approval to spend being granted once the scheme has progressed through the Assurance Process to Decision Point 5 (Full Business Case with Finalised Costs).  This will bring the total project value to approximately £3.817m (£0.820m LGF, £2.997m ELENA).

 

(d)        That development costs of up to £0.180m are approved in order to pay the incurred development costs and to progress the scheme to Decision Point 5 (Full Business Case with Finalised Costs) from the Local Growth Fund, taking the total project approval to £0.820m).

 

(e)        That future approvals are made in accordance with the Approval Pathway and Approval Route outlined in the submitted report including at Decision Point 5 through a delegation to WYCA’s Managing Director following a recommendation by WYCA’s Programme Appraisal Team.  This will be subject to the scheme remaining within the tolerances outlined in the submitted report.