Issue - decisions

Rail Policy and Programme Development

10/07/2017 - Rail Policy and Programme Development

(iii)       To approve in respect of the Rail Policy and Programme Development programme:

 

(a)   That the programme progresses through Decision Point 2 and work commences on Activity 6, Delivery;

 

(b)   Capital expenditure of £300k to deliver the Rail Policy and Programme Development programme, funded from the LTP IP3 programme.

 

(c)    The Assurance Pathway and Tolerances as recommended by the PAT. This approval route will be subject to the schemes remaining within the tolerances outlined.