CCTV Digital Upgrade

10/07/2017 - CCTV Digital Upgrade

(i)         To approve in respect of the Bus Station CCTV digital upgrade project:

 

(a)   That the project progresses through Decision Point 5 (Full Business Case with Finalised Costs) and commences work on Activity 6, Delivery;

 

(b)   The increase in total project capital costs from £550k and grant approval for capital expenditure of £1.095m to deliver the Bus Station CCTV digital upgrade project, funded from the LTP IP3 and NPIF programmes.

 

(c)    The Assurance Pathway and Tolerances as recommended by the PAT. This approval route will be subject to the schemes remaining within the tolerances outlined.