(c)        In respect of ULEV Taxi Scheme - Decision Point 2 (Case Paper) -

 

(i)                 That the ULEV Taxi Scheme proceeds through Decision Point 2 and the work commences on Activity 5: (Full Business Case with Finalised Costs).

 

(ii)               That an indicative approval to the total project value of £3.180m be given, with ultimate approval to spend being granted once the scheme has progressed through the Assurance Process to Decision Point 5 (Full Business Case with Finalised Costs).

 

(iii)             That development costs of £25,000 in order to progress the scheme to Decision Point 5 (Full Business Case with Finalised Costs) from the OLEV grant be approved.

 

(iv)              That the future approvals at Decision Point 5 are made through a delegation to WYCA’s Managing Director. This Approval Route will be subject to the scheme remaining within the tolerances outlined above.