(e) In respect of Rail Park and Ride Phase 2 - Decision Point 2 (Case Paper) -
(i) That the Rail Park and Ride Phase 2 programme proceeds through Decision Point 2 and the work commences by the individual schemes on Activity 4 (Full Business Case).
(ii) That an indicative approval be given to the total programme value of £12.5m with ultimate approval to spend being granted once the individual schemes have progressed through the Assurance Process to Decision Point 5 (Full Business Case with Finalised Costs). This will be funded through WY+TF funds re-profiled from Phase 1 of Rail Park and Ride.
(iii) That development costs of £477,100 in order to progress the schemes to Decision Point 4 be approved.
(iv) That the individual schemes return to Investment Committee and WYCA for approval at Decision Point 4 (Full Business Case) where the proposed Approval Route for Decision Point 5 through a delegation to WYCA’s Managing Director will be confirmed. This Approval Route will be subject to the schemes remaining within the tolerances outlined above.