Rail Park and Ride Package Phase 1 - Knottingley

30/06/2017 - Rail Park and Ride Package Phase 1 - Knottingley

(d)        In respect of Knottingley Rail Station P&R - Decision Point 2 (Case Paper) -  

 

(i)                 That the Knottingley Rail Station Park and Ride project proceeds through Decision Point 2 and the work commences on Activity 4 (Full Business Case).

 

(ii)               That an indicative approval be given to the total project value of £1.78m with ultimate approval to spend being granted once the project has progressed through the Assurance Process to Decision Point 5 (Full Business Case with Finalised Costs).

 

(iii)             That development costs of £474,259 in order to progress the scheme to Decision Point 4 to be funded from the WY+TF be approved.

 

(iv)              That the future approvals at Decision Point 4 are made through a delegation to WYCA’s Managing Director following consideration and recommendation by Investment Committee. Approval at Decision Point 5 will be made through the delegation to WYCA’s Managing Director. This Approval Route will be subject to the scheme remaining within the tolerances outlined above.