Decision details

Cycle Network Development

Decision Maker: Transport Committee

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

Funding for West Yorkshire Cycle Network Development in 2017/18 and 2018/19 has been included in the approved LTP IP3 programme with the agreement of all partners, to enable activities that support WYCA and District partners in developing local and strategic cycling networks.

Decision:

(vii)      To approve in respect of the Strategic Cycle Network Development programme:

 

(a)   That the programme progresses through Decision Point 2 and work commences on Activity 6, Delivery;

 

(b)   Capital expenditure of £100k to deliver Strategic Cycle Network Development programme, funded from the LTP IP3 programme.

Report author: Liz Hunter

Publication date: 10/07/2017

Date of decision: 07/07/2017

Decided at meeting: 07/07/2017 - Transport Committee

Effective from: 19/07/2017