Funding for Rail Policy and Programme
Development is included in the approved LTP IP3 programme to
provide a budget for a range of on-going rail policy and programme
development work. The main purpose is to develop a new rail policy
and strategy for the Leeds City Region, and following on from that,
determine the future programme of rail schemes to feed into
WYCA’s and other regional, sub-regional and national delivery
partners’ scheme pipelines.
(iii) To approve in respect of the Rail Policy and Programme Development programme:
(a) That the programme progresses through Decision Point 2 and work commences on Activity 6, Delivery;
(b) Capital expenditure of £300k to deliver the Rail Policy and Programme Development programme, funded from the LTP IP3 programme.
(c) The Assurance Pathway and Tolerances as recommended by the PAT. This approval route will be subject to the schemes remaining within the tolerances outlined.
Report author: Liz Hunter
Publication date: 10/07/2017
Date of decision: 07/07/2017
Decided at meeting: 07/07/2017 - Transport Committee
Effective from: 19/07/2017