Decision details

Bus Hotspots

Decision Maker: Transport Committee

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval of expenditure to deliver a programme of minor highway works aimed at improving bus service punctuality.

Decision:

(ii)        To approve in respect of the Bus Hotspots programme:

 

(a)   That the programme progresses through Decision Point 5 (Full Business Case with Finalised Costs) and work commences on Activity 6, Delivery;

 

(b)   Capital expenditure of £1.037m to deliver the Bus Hotspots programme, funded from the LTP IP3 and NPIF programmes.

 

(c)    The entering into a Funding Agreement with Bradford Council for expenditure of up to £674,400, with Calderdale Council for expenditure of up to £20,000, Kirklees Council for expenditure of up to £168,700, and Wakefield Council for expenditure of up to £173,500.

 

(d)   The Assurance Pathway and Tolerances as recommended by the PAT. This approval route will be subject to the schemes remaining within the tolerances outlined.

Report author: Dave Pearson

Publication date: 10/07/2017

Date of decision: 07/07/2017

Decided at meeting: 07/07/2017 - Transport Committee

Effective from: 19/07/2017