Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval of LEP loan to accelerate the development of the Gateway 45 area within the Leeds Enterprise Zone.
In respect of LEP Loan - Gateway 45 - Decision Point 4 (Full Business Case)
(i) That the Gateway 45 loan proceeds through Decision Point 4 and the work commences on Activity 5 (Full Business Case with Finalise costs).
(ii) That an indicative approval to the total loan value of £3.3m be given, with ultimate approval to the loan being granted once the project has progressed through the Assurance Process to Decision Point 5 (Full Business Case with Finalised Costs).
(iii) That Leeds City Council are instructed that the current charge held as security for the earlier £3m LEP loan is released and imposed solely on part of the site.
(iv) That the approval of the loan agreement at Decision Point 5 be made through the delegation to WYCA’s Managing Director, subject to the scheme remaining within the tolerances set out above.
Report author: Sally Hinton
Publication date: 30/06/2017
Date of decision: 29/06/2017
Decided at meeting: 29/06/2017 - West Yorkshire Combined Authority
Effective from: 11/07/2017