Rail Park & Ride Package (Phase 2a)

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Programme to increase car parking capacity at identified stations.

Decision:

(e)        In respect of Rail Park and Ride Phase 2 - Decision Point 2 (Case Paper) -

 

(i)                 That the Rail Park and Ride Phase 2 programme proceeds through Decision Point 2 and the work commences by the individual schemes on Activity 4 (Full Business Case).

 

(ii)               That an indicative approval be given to the total programme value of £12.5m with ultimate approval to spend being granted once the individual schemes have progressed through the Assurance Process to Decision Point 5 (Full Business Case with Finalised Costs). This will be funded through WY+TF funds re-profiled from Phase 1 of Rail Park and Ride.

 

(iii)             That development costs of £477,100 in order to progress the schemes to Decision Point 4 be approved.

 

(iv)              That the individual schemes return to Investment Committee and WYCA for approval at Decision Point 4 (Full Business Case) where the proposed Approval Route for Decision Point 5 through a delegation to WYCA’s Managing Director will be confirmed. This Approval Route will be subject to the schemes remaining within the tolerances outlined above.

Report author: Peter Coello

Publication date: 30/06/2017

Date of decision: 29/06/2017

Decided at meeting: 29/06/2017 - West Yorkshire Combined Authority

Effective from: 11/07/2017