Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Part of the programme to increase car parking capacity at identified stations to support more travel into urban centres by rail.
(d) In respect of Knottingley Rail Station P&R - Decision Point 2 (Case Paper) -
(i) That the Knottingley Rail Station Park and Ride project proceeds through Decision Point 2 and the work commences on Activity 4 (Full Business Case).
(ii) That an indicative approval be given to the total project value of £1.78m with ultimate approval to spend being granted once the project has progressed through the Assurance Process to Decision Point 5 (Full Business Case with Finalised Costs).
(iii) That development costs of £474,259 in order to progress the scheme to Decision Point 4 to be funded from the WY+TF be approved.
(iv) That the future approvals at Decision Point 4 are made through a delegation to WYCA’s Managing Director following consideration and recommendation by Investment Committee. Approval at Decision Point 5 will be made through the delegation to WYCA’s Managing Director. This Approval Route will be subject to the scheme remaining within the tolerances outlined above.
Report author: Peter Coello
Publication date: 30/06/2017
Date of decision: 29/06/2017
Decided at meeting: 29/06/2017 - West Yorkshire Combined Authority
Effective from: 11/07/2017