Business Growth Programme - Decision Point 2 (Case Paper)

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval in principle of additional funding to allow continuation of the Business Growth Programme.

Decision:

In respect of the Business Growth Programme - Decision Point 2 (Case Paper)

 

(i)         That the Business Growth Programme proceeds through Decision Point 2 and the work commences on Activity 5 (Full Business Case with Finalised Costs).

 

(ii)        That an indicative approval to the total scheme value of £9m be given, with ultimate approval to spend being granted once the project has progressed through the Assurance Process to Decision Point 5 (Full Business Case with Finalised Costs).

 

(iii)       That the future approval at Decision Point 5 be made through a delegation to WYCA’s Managing Director following consideration and a recommendation by Investment Committee. This Approval Route will be subject to the scheme remaining within the tolerances outlined above.

Report author: Henry Rigg

Publication date: 29/06/2017

Date of decision: 29/06/2017

Decided at meeting: 29/06/2017 - West Yorkshire Combined Authority

Effective from: 12/07/2017