Decision details

WYCA Rail Park and Ride Programme – Mytholmroyd pre-nesting works

Decision Maker: Director, Finance & Commercial Services

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To allow Network Rail to complete pre-nesting works by 1st March 2018 to ensure the main contract to deliver 203 new car parking spaces at Mytholmroyd station, as part of the WY+TF Rail Park & Ride Phase 1 Programme, can be delivered without further slippage.

Decision:

To approve the Change Request for the Rail Park & Ride Programme - Mytholmroyd pre-nesting works to allow for de-vegetation works to be carried out in advance of the 2018 nesting season and to approve advanced spend of up to £30,000 from the original total scheme funding allocation of £3.64m to progress this work.

To approve WYCA entering into an Implementation Agreement with Network Rail for the value of up to £30.000.00 for the works to be undertaken.

Alternative options considered:

Option 1 -
Option 2 -
Option 3 -

Publication date: 16/02/2018

Date of decision: 02/02/2018